|
Sacramento City Unified School District Bond Oversight Committee
History and Performance
Jan 1998 through Nov. 2002
BACKGROUND. In January of 1998
the League learned the Sacramento City Unified School District (SCUSD)
was considering another school rehabilitation bond, following defeat
of an earlier $225 million bond Measure U, which failed because
the community did not believe the District would spend the bond
money wisely. The League advised the District that for a future
bond Measure they should have a Master Plan assessing the repairs
and modifications necessary; agreement that all bond proceeds were
to be used for one time spending only; agreement that spending levels
of off-set operations and maintenance costs should not be diverted
to reoccurring costs such as salaries, but rather used for other
one time costs such as computers, bond sinking funds and extra class
room construction to support classroom reductions as examples; endorsement
of an Oversight Committee as proposed by the Sacramento Metro Chamber
of Commerce (SMCC); and other fiscal controls. Our understanding
is that in preparing for the bond issue, district staff reduced
the original $250 million bond sum to $195 million, without a change
in scope of work. As a result, cost figures for the new bond were
below the cost of the required work. However, it was anticipated
that if the bond passed, the District would be eligible for additional
money from local and state matching funds. The overall plan covered
a new high school in the Rosemont area, and a school facilities
repair program, to be financed by the $195 million bond Measure
and other federal and state money. The SMCC, in conjunction with
Sacramento Area Congregations Together (ACT) formed a Blue Ribbon
Panel to advise the SCUSD on the marketing of the bond Measure.
In March 1999, Director Pat Kelly volunteered to become the League
observer of the activities of the Panel. A presentation was made
to the League Board in June 1999, who questioned the lack of specifics
with regard to costs over the term of the bonds, and cost allocations
with relation to Capital vs. Operations and Maintenance as bond
money became available.
DISTRICT RESOLUTIONS 2070A and 2070B.
The District approved Resolution 2070A which ordered the bond election,
and set the specifications for the bonds and the manner in which
they would be sold. Resolution 2070 B was passed to satisfy critics
wherein Item 4 stated, The district shall fund maintenance
and operations as necessary to properly maintain district facilities
to guarantee that the maintenance budget would not be reduced to
pay for other salaries.
THE SPECIAL ELECTION. The $195
million bond Measure, if passed was estimated to cost property owners
about $46 a year per $100,000 of assessed value. From the outset,
facing the requirement of a two-thirds majority vote for bond passage,
the District's plan was to use a Special Election, slated for October
19, 1999, which would cost the District about $322,000, as no regular
election was scheduled until the following March, which could jeopardize
the District's chances for matching funds. Their strategy was to
convince election officials to use public school sites as polling
places, and to schedule a "Back to School Day" on the
same date for parents who would be inclined to vote for school bonds.
As was the case with the San Juan School District, they hoped to
win support of the Taxpayers League by providing the same provisions
for an Oversight Committee (OC) and an independent audit to ensure
money was spent on school improvements only. The League's Board,
in June 1999 agreed the District's facilities needed extensive repair,
and voted to remain neutral with respect to the Measure, leaving
it to the voters to decide whether they were willing to encumber
themselves with long-term indebtedness. The bond Initiative became
Measure E, and was passed in October with 78.3% of the vote.
THE OVERSIGHT COMMITTEE. On
November 12th, The SMCC invited the League to join the OC, and Director
Pat Kelly, a professional state auditor was selected to represent
the League. The limiting responsibilities and purposes enumerated
by the district after committees formation are:
-
Selection of an independent auditor
for the school bond.
-
Receive an annual auditor's report
and communicate the findings to the board and general public.
-
Ensure that funds are used only
on school building improvements, not district salaries or administration.
-
Provide regular reports to the
President of the Sacramento City Unified District Board of Trustees
that the expenditures match those promised during the bond campaign.
In addition, release these general findings to the general public.
-
Review the districts maintenance
effort to ensure proper maintenance of school buildings after
repair and renovation.
-
Review districts building
repair funding plan comprised of local and state bond funds,
and other funding sources.
The first meeting of the OC was in
January 2000. Despite promises made prior to public vote, bond language
merely indicated the only specific task assigned the OC was to ensure
that bond money was spent only on construction, not salaries, and
the OCs original leader and district officials seemed to feel
that that was its only job. However, other OC members saw the obligation
to the public was to warrant that the program was conducted properly.
OC members also questioned the basic study and pressed for its revision
based on the following: A) The figures had no relevance to the work
proposed, B) Figures didnt account for inflation, C) Soft
costs (architects, engineers, inspectors, etc.) were far too
low, D) There was no criteria for determining the sequence of work,
and E) The scope had not been updated to show additions of recent
discoveries or deletion of work already done by district maintenance
forces in the interim. The Board authorized OC to contract with
KPMG for a study. ($12,000 fee). KPMG recommended that district
essentially do what OC members had been requesting.
OVERSIGHT PROBLEMS. After the
first several meetings, the committee met quarterly, not enough
to keep abreast of events and to pursue investigations. Essentially
no oversight was accomplished. Recognizing that review of every
aspect of every project is not feasible or appropriate, sampled
review would have been a responsible approach to oversight responsibility.
However, the OC either was denied, or not afforded, the opportunity
to perform reviews. The district blunted review efforts by prolonged
discussions of format, content and statements that added staff would
be required, and requests to see the district's own documents, forms,
etc. was entirely turned aside. OC was in contact with only a few
managers of the effort. Little knowledge was gained of the broad
organization. The OC was not able to identify personnel or procedures
used to ascertain scope of projects, selection of consultants (architects,
engineers, etc.), contracts with same, review project plans and
specifications, review construction contract documents, award construction
contracts, inspect construction, authorize payments, authorize change
orders, and coordinate with school personnel. OC was unable to review
performance or any of the documents mentioned above. OC understood
that Architects and Engineers prepared plans. However, a project
manager was also encountered whose role seemed very broad,
but was never spelled out. Fees paid were also not divulged to OC.
Also, without knowing the tasks that the consultant project
manager performed, the OC could not rule out that he was paid
from bond money for work that is properly a district cost.
The prioritization of the schools to
be refurbished and the elements to be done apparently was decided
in an expedient fashion. The process and the criteria used were
often not divulged. Detailed lists of the elements in a construction
project were not provided to OC and were effectively denied. OC
was even not supplied plans or written scope of the projects that
members were authorized to visit and were therefore unable to compare
contracted work with that listed. Appropriateness of work accomplished
was not possible due to the limited information and access granted
to OC. OC did not attempt to review the work listed to be accomplished
at the individual schools. Casual observation indicated that school
personnel were not aware of the distinction between those elements
that would logically be contracted (funded by bond money), and those
that could be routinely be done by district forces.
A format was finally established and
was provided on a few projects long after they were completed. Unfortunately,
the reports were not timely and items were, and are, too general
in nature. The only reported items are: Total Expenditure, Budget,
Amount Over, State Contribution, District Cost and Soft Cost Amount.
Copies of district documents such as Contractors Schedule
of Values and Change Orders, which would detail
expenditures, are not available. Neither were lists of Soft
Costs (fees of professional consultants and inspectors).
The disposition of bond funds after
receipt was not available, nor was account cash flow documents.
Details regarding the use of borrowed money and its cost were not
disclosed. After almost two years, it seems the OC cannot reasonably
stipulate that expenditures match those promised individual schools,
and that election goals are being met. The districts true
goal seems to be, Get money & spend it, whereas
the goal should be, Spend the money properly. Further,
the maintenance effort review has consisted only of conversations
with the district manager. No field verifications have taken place.
An example of concerns was reported in the Sac Bee on Oct 3, 2002.
The board deleted 3 roofers to help remedy a budget shortfall, saving
about $148,000 per year. As quoted, district personnel stated that
roofers were not needed since many reroofings had been done with
bond money. Deleting district construction related positions has
the effect of moving maintenance and construction money to fund
other activities, meaning that the work that those maintenance positions
would have done must now be done by bond money projects. Effectively,
district salaries are being replaced by bond funds to accomplish
the work. Thats something the board said that it would not
do.
With regard to Rosemont High School,
no information of major expenditure of bond money was provided,
except the budgeted cost. OC saw nothing of lists of land acquisition
consultants, their roles and fees; costs of land, studies and reports
(EIR, etc.); site studies and reports; professionals employed and
their fees; elements to be included in the school; and the schedule
or phasing of the project. Appointments to review sites were difficult
to obtain, and information needed to identify work at the site were
not available. Communication between the OC and district, and between
the chairs and members was not sufficient to keep issues current
and meaningful. The feeling is that the OC has not strongly enough
sought the information necessary to fulfill its oversight obligation.
COMMITTEE ACCOMPLISHMENTS. All
committee members that were active deserve to be acknowledged for
their expertise, value, and efforts. That they accomplished so little
probably resulted from the original leaders and the districts
perception of their charge. Despite that, the Committee did prod
the district to set in progress a realistic listing of the Scope
of Work that needed to be accomplished, a proper estimate
of the cost of the work, and the establishment of the criteria to
be used in determining the order in which the work is to be done.
District established the Facilities Strategic Planning Committee
(FSPC) to accomplish that task. However, the OC had seen no results.
OC did sample districts performance in coordinating work and
scope of work with the project school principal, staff and its parent
organizations. OC contracted with districts independent auditor
to verify that bond funds were spent only on construction,
and the Auditor indicated conformance. OC contracted with KPMG Consulting
to evaluate districts Project Management Plan.
OC began an inquiry into districts preventative maintenance
program to verify maintaining of pledged budget. It also began review
of maintenance operational procedures and responsibilities. OC identified
the districts unsatisfactory performance in requesting state
matching funds. And the OC worked to encourage recruiting of replacement
committee members.
RECOMMENDATION THE LEAGUE END PARTICIPATION
IN OVERSIGHT COMMITTEE. Citing two years of dissatisfaction
with the cooperation to, management of, and lack of effectiveness
of the SCUSD Oversight Committee, League Representative Pat Kelly
recommended the League withdraw from further participation in the
activity. The concerns were documented in this report, and presented
to the League Board. The Board reviewed the report, voted unanimously
to withdraw from further participation in the OC, and directed a
letter be sent to the SCUSD advising of its action.
Joe Sullivan - President
|